Hyderabad, The Deputy Chief Minister Md. Mahmood Ali stated in the Legislative Assembly today that administrative sanction has been accorded for an amount of Rs.9.60 crore for construction of CC Ramp Road/Motor-able track and four wheelers hilltop Parking lot connecting to the existing Highway to Dargah Hzt Baba Sharfuddin, Pahadishareef, Ranga Reddy district. The construction work will start shortly.
Replying to a question of Akabaruddin Owaisi, Ahmed Bin Abdullah Balala and other MIM members, the Deputy Chief Minister said that n under phase two, construction of Road/Ramp to midlanding of steps at Moulali Dargah has been completed by the GHMC. Under Phase two, work from Midlanding of steps to Hill Top of Moulali Dargah with an estimated cost of Rs.25 crore is under progress. The construction work will be completed as soon as possible, he added.